Main Target:

The main objectives of WP2 are the following:

  • Definition of vehicle specifications based on vehicle simulation
  • Breakdown of vehicle specifications to requirements for all Key Technologies, subsystem and components
  • Definition of vehicle packaging concept
  • Overall vehicle safety concept

TRL:

Beginning of project: TRL 1 (basic principles observed)

Expected TRL end of project: TRL 2 (formulation of technology concept)

Main Tasks:

  • 2.1: Vehicle Specification Definition
  • 2.2: Preliminary Packaging Study
  • 2.3: Breakdown of Vehicle Specifications to Key Technologies
  • 2.4: Preliminary Vehicle Safety Concept

Methods:

  • Vehicle simulation with AVL CRUISE
  • PEM System simulation with CRUISE M Flow
  • 3D Packaging studies with CATIA or ProE
  • Techno-economic analyses and modelling for powertrain costs
  • Hazard and risk assessment (HARA)

Main Milestones:

MILESTONE 8: Target vehicle platform defined

MILESTONE 9: Key Technologies Specifications ready

Main Deliverables:

DELIVERABLE 6: Vehicle Requirement Report

DELIVERABLE 8: Key Technologies Specifications